Scrum uses a series of coordinated meetings to manage the development process. Which of the following is held at the start of each sprint? During this meeting the product owner and development team negotiate which product backlog items the team will attempt during the next sprint.

asked
User Abarax
by
8.2k points

1 Answer

5 votes

Answer:

Sprint planning meeting

Step-by-step explanation:

Sprint planning is a joint effort involving a person on the team who is responsible for managing the process and organizing the meeting.

It also involves a Product Owner clarifying the specifics of the product backlog items and their respective acceptance requirements, and the Entire Agile Team identifying the work and effort needed to fulfill their sprint engagement.