Sandra, the operations manager of the Zara clothing chain, is informed that the summer line requires certain materials that are not available locally. She recalls having used the same raw materials two summers ago from a niche supplier. Which of the following should she use to solve this issue

asked
User Paleonix
by
7.5k points

1 Answer

5 votes

Answer:

MRP (Material Requirement Planning)

Step-by-step explanation:

Material Requirements Planning (MRP) is a calculation system for the components and materials necessary to produce goods.

All of this consists of three principal steps:

  • stock of on-hand components and materials,
  • recognize which added bits are required and,
  • afterwards schedule their manufacturing or purchase.