asked 76.8k views
0 votes
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:HoursWait time 12.7Process time 1.8Inspection time 0.2Move time 4.4Queue time 6.1The delivery cycle time was:

asked
User GordonW
by
8.4k points

1 Answer

2 votes

Answer:

The delivery cycle time was 25.2 hours

Step-by-step explanation:

Working notes:

Consider the following formula to solve the exercise

delivery cycle time=Wait time+Process time+Inspection time+Move time+Queue time

=(12.7+1.8+0.2+4.4+6.1)

which is equal to = 25.2 hours.