asked 130k views
0 votes
Which of the following responses identifies a common type of logical dependency used to sequence project activities?

a. last-in; last-out
b. finish-to-start
c. first-in; first-out
d. last-in; first-out

asked
User Edyta
by
8.6k points

1 Answer

6 votes

Answer:

b. finish-to-start

Step-by-step explanation:

Activity dependencies or activity relationships are of four types.

  • Finish-to-Start: Activity B cannot start until the activity A finishes.
  • Start-to-Start: The activity B cannot start until the activity A starts.
  • Start-to-Finish: The activity B cannot finish until the activity A starts.
  • Finish-to-Finish: The activity B cannot finish until the activity A finishes.

answered
User Rayniery
by
8.6k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.