A PERT network consists of activities linked by arrows. Suppose two of the activities on the network are labeled "A" and "B." An arrow from "A" to "B" indicates that

asked
User Prabhav
by
7.1k points

1 Answer

4 votes

Answer:

Task A must be completed before you can start with task B.

Step-by-step explanation:

A Program Evaluation Review Technique (PERT) network is a project management technique used to schedule, organize and coordinate tasks. It was first developed by the navy during the 1950s as a way to manage their submarine missile program.