In agile projects, overall planning is at a high level, and only the near-term work is planned in detail. The project work is conducted in iterations (sprints) that are normally: a. no more than one calendar year b. a variable length depending on project scope c. a fixed length of two or four weeks d. assigned to one person on the team

asked
User Oliver P
by
7.5k points

1 Answer

4 votes

Answer:

The answer is letter C.

Step-by-step explanation:

A fixed length of two or four weeks.