All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS) for a project EXCEPT: ​

a. Project teams may use a template or a WBS from a previous project as a starting point.
b. Project teams may jump start the WBS construction with a brainstorming session.
c. Project teams may adopt a top-down approach to construct the WBS.
d. Project teams may rely upon the project manager to create all levels of the WBS.

1 Answer

0 votes

Answer: option d

Step-by-step explanation:

Project teams must be proactive. Each member of the team should empowered and each member can share ideas and experience in order to make the WBS more precise.

answered
User SelvaMariappan
by
8.8k points