Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client be pleased or angry? Explain.

1 Answer

1 vote

Answer:

Probably not

Step-by-step explanation:

To me I think they planed to give the money to you guys for it try and put a little more in the project. The most important part is if the client is happy about the advertisement.