True or False. Each organization or subcontractor responsible for a group or type of activities should always designate an inexperienced individual to estimate the durations for all the activities for which the organization or subcontractor is responsible.

asked
User MazBeye
by
8.7k points

1 Answer

3 votes

Answer:

False

Step-by-step explanation:

No one should ever designate an inexperienced anything (e.g. engineer, accountant, salesman, etc.) to estimate a budget or an activities schedule. Usually people that estimate any kind of activity, should at least have some experience doing that activity, so that they know what is normal or achievable in a reasonable time.