One grocery clerk can stock a shelf in 20 min. A second clerk requires 45 min to stock the same shelf. How long would it take to stock the shelf if the two clerks worked together?

1 Answer

3 votes

Answer:

clerk A and clerk B can simultaneously stock a shelf in
(180)/(13) minutes

Step-by-step explanation:

Let the first clerk be A and the second clerk be B

A can stock a shelf in 20 min

B can stock a shelf in 45 min

Consider the complete work to be W

A’s rate of stocking =
(W)/(20) per minute

B’s rate of stocking =
(W)/(45) per minute

When, A and B work simultaneously, rate of work done =
(W)/(20)+(W)/(45)

Total work done simulatenously =
(W)/((W)/(20)+(w)/(45))

=
(20 * 45)/(20+45)

Therefore, clerk A and clerk B can simultaneously stock a shelf in
(180)/(13)
minutes