asked 114k views
0 votes
A manufacturer's average work-in-process inventory for Part #1234 of a particular car model is 1,250 parts. The workstation produces parts at the rate of 150 parts per day. What is the average time a part spends at the workstation?

a. More than 4 but less than or equal to 6 days.
b. More than 6 but less than or equal to 8 days.
c. More than 8 but less than or equal to 10 days.
d. More than 10 days.

asked
User Garee
by
8.0k points

1 Answer

1 vote

Answer:

C. More than 8 but less than or equal to 10 days.

answered
User BeeNoisy
by
8.1k points