Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?

1 Answer

3 votes

Answer:

Padding estimates.

Step-by-step explanation:

Padding the budget means making the budget proposal larger than the actual estimates for the project. This is done either by increasing a project's expenses or decreasing its expected revenue.