asked 132k views
4 votes
Marlo Stanfield's operation also uses large quantities of prepaid cell phones, on average 1500 per week with a standard deviation of 145. The lead time for their own brand of prepaid cell phones is three weeks and they have a lot size of 350 phones. To ensure they never run out, they keep a safety stock of 500 phones with Proposition Joe. What is the cycle service level under this policy?

a. 0.9398
b. 0.9833
c. 0.9768
d. 0.9512

asked
User Emehex
by
8.7k points

1 Answer

4 votes

Answer:

c. 0.9768

Step-by-step explanation:

Lead time

Safety stock 500

Standard deviation 145

Safety stock = z * Standard deviation *
√(L)

500 = z * 145*
√(3)

500 = z * 251.14

Z = 1.990863

Therefore, for this Z value, we obtain the option c. 0.9768

answered
User Glv
by
8.3k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.