The gross requirements of a given component part are determined from ______________________.

a) scheduled receipts plus projected available
b) gross requirements of the parent
c) planned orders of the parent
d) projected available of the end item
e) planned orders of the end item

1 Answer

7 votes

Answer: The correct answer is "c) planned orders of the parent".

Explanation: The gross requirements of a given component part are determined from planned orders of the parent

Without the release of planned orders from immediate parents, the gross requirements of a given component part could not be determined.