Gold Company uses a plantwide overhead rate with machine hours as the allocation base. 
 
Use the following information to solve for the amount of machine hours estimated per unit of product RST. 
 
Direct material cost per unit of RST $15 
 
Total estimated manufacturing overhead $300,000 
 
Total cost per unit of RST $80 
 
Total estimated machine hours 150,000 
 
MH Direct labor cost per unit of RST $232 
 
1 MH per unit of RST. 
 
2 MH per unit of RST. 
 
20 MH per unit of RST. 
 
37.5 MH per unit of RST. 
 
38 MH per unit of RST. 
 
 
 
the amount of machine hours estimated per unit = divide total overhead / the number of direct labor hours 
300,000/150,000 =2 
 