asked 29.2k views
0 votes
a pipeline is laid at a rate of 1/8 mile per day.How many miles of line would be completed in 29 1/2 days​

asked
User Dribbel
by
8.3k points

1 Answer

5 votes

Answer:

In 29 1/2 days, the total pipe laid is
((59)/(16)) mile.

Explanation:

The length of pipe laid in 1 day = 1/8 mile

So, the length of pipe laid in half day = half of (1/8 mile)

=
(1)/(2)  * (1)/(8)  = (1)/(16)  \textrm{mile}

Now, 29 1/2 days on simplification means 29 and half day.

So, length of pipe in 29 days =
29 * (1)/(8)  = (29)/(8) mile

Now adding the length laid in half day =
(29)/(8)  + (1)/(16)  = (29 (2) + 1)/(16)  = (59)/(16)  \textrm{mile}

So, in 29 1/2 days, the total pipe laid is
((59)/(16)) mile.

answered
User Henry Twist
by
8.6k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.