f all you knew about a production system was that total daily output was 400 units and the total labor necessary to produce the 400 units was 350 hours, and the total materials used were 425 units, what kind of productivity measure could you use to compute productivity? Partial measure Multifactor measure Total measure

asked
User Pyprism
by
7.2k points

2 Answers

4 votes
partial measure would b it
answered
User Channing
by
8.2k points
2 votes

Answer:

Partial measure

Step-by-step explanation:

answered