asked 51.2k views
24 votes
Given the following data for the number of defects per spool of cable.

OBSERVATION

1 2 3 4 5 6 7 8 9 10 11 12 13 14
Number of defects 2 3 1 0 1 3 2 0 2 1 3 1 2 0
a.
Determine three-sigma control limits using the above data. (Do not round intermediate calculations. Round your final answers to 2 decimal places. Leave no cells blank - be certain to enter "0" wherever required. Round up any negative control limit value to zero.)

UCL
LCL
b. Is the process in control?
Yes
No

asked
User Tortuga
by
8.1k points

1 Answer

10 votes

Answer:

a.

UCL = 5.17

LCL = 0.00

b.) Yes

The process is in control

Step-by-step explanation:

Number of observations = 14

Total number of defects = 2+3+1+0+1+3+2+0+2+1+3+1+2+0 = 21

X = (number of defects)/(observation)

X = 21/14

= 1.50

UCL = upper control limit

= X+z√X

= 1.5+3√1.5

= 1.5+3.674234614

= 5.17 to 2 decimal places

LCL = lower control limit

= X-z√X

= 1.5-3√1.5

= -2.17

= 0.00

B.)

From the above, we have the number of defects to be within the control limits of 0 to 5.17, therefore we can conclude that the process is in control

answered
User Ext
by
8.8k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.