What phase of program planning is the execution of the plan?

a. Evaluation
b. Development
c. Implementation
d. None of the above.

asked
User Zyash
by
8.2k points

1 Answer

7 votes

Answer:

Implementation phase

Step-by-step explanation:

The Implementation phase is the phase that involves the actual execution of the work that is the work starts to be done on the ground or site.

The Evaluation is the phase involving the estimation, planning and calculations.

Development phase deals with the tasks related to the arrangement and planning of the things required for the implementation of the work.