Kitty Co. broke ground on its new building on March 1, 2018, and completed construction November 30, 2018. Kitty made the following expenditures in conjunction with this project:

Date Expenditure
April 1, 2018 $ 450,000
June 1, 2018 200,000
September 1, 2018 400,000
November 30, 2018 100,000
Kitty's cumulative weighted average expenditures on this project would be

asked
User Cnsvnc
by
8.0k points

2 Answers

5 votes

Answer:

$595,833

Step-by-step explanation:

answered
User MKay
by
8.3k points
5 votes

Answer:

$595,833

Step-by-step explanation:

You add all and divide.