After cost overruns of the solar project, $10 million was already spent and unrecoverable. It was going to cost $12 million more in order to complete the project, and now society somehow needs to make the rational choice toa. continue with the project provided that the additional solar electricity is worth more than $10 million.b. continue with the project provided that the additional solar electricity is worth more than $32 million.c. continue with the project provided that the additional solar electricity is worth more than $22 million.

asked
User Jstejada
by
8.4k points

1 Answer

3 votes

Answer:

a. continue with the project provided that the additional solar electricity is worth more than $10 million.

Step-by-step explanation:

It is provided that after cost overruns of the project is $10 million, which can never be recovered, thus, it is a kind of sunk cost.

Sunk cost is the cost which is made previously, and now in no manner will affect the decision, as cannot be recovered.

Therefore, such cost is ignored.

Further provided additional cost will be $12 million, therefore, now the society shall make a rational choice whether to continue the project providing solar electricity of $10 million, as in case of amount of solar energy is $32 million or $22 million, then the choice is obvious to accept,

Rational choice will be for solar electricity worth $10 million.

Therefore, correct statement is

a. continue with the project provided that the additional solar electricity is worth more than $10 million.