asked 84.5k views
5 votes
A company may use job costing to assign costs to different product lines and then use process costing to calculate uniot costs within each product line. T/F

1 Answer

0 votes

Answer:

The statement is "TRUE"

Step-by-step explanation:

The process costing is used when there is mass production of equal or similar products, it helps to assign all the costs required to produce a line of products.

Job cost is used for calculating costs for different jobs (referring to services) or products (referring to manufacturing). It works under the thought that every job/product is different and the supplies needed are different on each.

Both are methods to calculate costs, the usage of one or another varies depending on the type of business.

answered
User Jim Nasby
by
8.0k points

No related questions found