asked 218k views
4 votes
Which of the following is true about the job-order cost sheet?

a. It is prepared for every job.
b. It is the primary document for accumulating all costs related to a particular job.
c. It is subsidiary to the work-in-process account.
d. It contains all information pertinent to a job.
e. All of these choices are correct.

1 Answer

0 votes

Answer:

The correct answer is c) It is subsidiary to the work-in-process account

Step-by-step explanation:

It is used as an account book to the work in process account because it contains all details about the job in the process.

answered
User Tommyk
by
8.4k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.