All members of a construction crew work at the same pace. Four of them working together can pour a foundation in 32 hours. How many hours would the job take if the number of workers:

decreased 2 times

1 Answer

4 votes

Answer:

It would take them 64 hours. However, this is only true if they decrease by two in the end. The question is not very specific.