14 workers, working at the same pace, can lay 36000 bricks in one day. How many workers will be needed to lay 54000 bricks in the same period of time?

PlZ And ThanKS

asked
User Xaver
by
8.2k points

2 Answers

7 votes

Answer: 22 workers

Explanation:

answered
User Jeff Hardy
by
8.4k points
0 votes

Answer: 21 workers

Explanation:

answered
User Tyro Hunter
by
8.0k points