14 workers, working at the same pace, can lay 36000 bricks in one day. How many workers will be needed to lay 54000 bricks in the same period of time?

asked
User Klinky
by
8.0k points

2 Answers

5 votes

Answer:

21 workers would be your answer.

answered
User Yevhenii Shlapak
by
8.2k points
3 votes


\bf \begin{array}{ccll} workers&bricks\\ \cline{1-2} 14&36000\\ x&54000 \end{array}\implies \cfrac{14}{x}=\cfrac{36000}{54000}\implies \implies \cfrac{14}{x}=\cfrac{2}{3} \\\\\\ 42=2x\implies \cfrac{42}{2}=x\implies 21=x