On April 1st, Bob the Builder entered into a contract of one-month duration to build a barn for Nolan. Bob is guaranteed to receive a base fee of $4,500 for his services in addition to a bonus depending on when the project is completed. Nolan created incentives for Bob to finish the barn as soon as he can without jeopardizing the structural integrity of the barn. Nolan offered to pay an additional 30% of the base fee if the project finished 2 weeks early and 10% if the project finished a week early. The probability of finishing 2 weeks early is 30% and the probability of finishing a week early is 60%. What is the expected transaction price with variable consideration estimated as the expected value? Multiple Choice $5,175 $4,500 $6,175 $4,275

asked
User Edumike
by
8.0k points

1 Answer

3 votes

Answer:

a. $5,175

Step-by-step explanation:

Expected transaction price with variable consideration estimated as the expected value = $4,500 + (30%*$4,500*30%) + (10%*$4,500*60%) + (0%*$4,500*10%)

= $4,500 + $405 + $270 + $0

= $5,175

So, the expected transaction price with variable consideration estimated as the expected value is $5,175

answered
User Linkliu Mayuyu
by
8.6k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.