A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?

asked
User Louis
by
7.7k points

1 Answer

4 votes

Answer:

1

Step-by-step explanation:

The Formula for calculating Slack Time is as below:

Slack Time = Latest Completion Time - Earliest Completion time

When Latest Completion Time = 6 ; Earliest Completion time = 5

Slack Time = 6 - 5

Slack Time = 1

Thus, the slack time for the activity is 1 . The essence of calculating this is to prevent delays in the project completion.