asked 65.1k views
4 votes
The priority rule which processes jobs according to the smallest ratio of due date to processing time is:________

1 Answer

5 votes

Answer: critical ratio

Step-by-step explanation:

The priority rule which processes jobs according to the smallest ratio of due date to processing time is refered to as the critical ratio.

The critical ratio (CR) is typically used in sequencing work especially during projects or in organizations. For this sequencing, the job that has the lowest critical ratio will be the one that will have to be scheduled first for processing.